News

Wansford Bridge – Update

From:  Charlotte Milner, Customer Liaison Officer | Peterborough Highway Services | Milestone Infrastructure

We want to inform you that works came to a stop on Wansford Bridge due to archaeological finding, due to this reason, we had to call in for specialists to assist.

We were held up by just over a week for a redesign and then it has subsequently pushed the works back. The road closure has therefore been extended until the 13th October.

We have managed to pull a little time back and could hopefully be done before the 13th October weather permitting as the stonework’s is weather sensitive due to using lime mortar.

For further information on the archaeological side of things, please see attached communications between our site managers and specialised teams.

If there is any way to distribute this within your local village newsletters/ booklet this would help get the information across to residents.

If you have any further queries, please do not hesitate to contact me

Charlotte Milner, Customer Liaison Officer | Peterborough Highway Services | Milestone Infrastructure, Office: PHS Depot, Dodson Way, Peterborough, PE1 5XJ    Mobile: 07354 901835